29 August
2007
Work on the new
building enters the final phase and the car park is newly tarmaced.
For more photos click here.

9 August
2007
Work is
continuing on the interior of the new building. For
more photos click here.

27 July
2007
The exterior is
now nearing completion with cladding and windows now complete.
The interior is now being fitted out. For
more photos click here.

12 June
2007
Brickwork and
cladding is now well underway. For
more photos click here.

1 June
2007
The roof and
concrete floors are in place now giving shape to the extension.
For
more photos click here.

17 May
2007
The floors and
stairs are put in place. For
more photos click here.

8 May
2007
The steelwork
starts to give the new extension some shape. For
more photos click here.

5 May
2007
The groundwork
nears completion as the concrete is poured for the foundations of
the new extension. For more
photos click here.

13 April
2007
Sub-contractor,
Roger Bullivant, drives 18 pilings to a depth of nearly 20 metres
as work progresses. For
more photos click here.

2 April
2007
The excavators
move in!! For
more photos click here.

30 March
2007
HETA Chairman, Graeme Stuart, visits
the site of the new training extension.
For more photos click here.

27 March
2007
The first turf
is cut for the new training facility. For
more photos click here.

29 November
2006
Contractors start ground
work, drilling holes for the new extension at HETA, Hull.
For
more photos click here.

|